The SunZia Wind and Transmission project came online in June, deploying over 900 wind turbines across central New Mexico and connecting to a 550-mile transmission line that now powers over 1 million homes across the Southwest and California. Pattern Energy, the project developer, said the turbines will prevent about 9 million metric tons of carbon dioxide from entering the atmosphere by next summer.

The project took 17 years from its 2006 proposal to reach operation. Financing and market demand posed larger obstacles than permitting delays, according to David Hayes, who served as deputy secretary of the Department of the Interior during the Obama administration. Hayes noted that the project obtained federal permits in 2015 but faced years of inaction afterward. The U.S. simply lacked sufficient electricity demand at that time, said Hunter Armistead, Pattern's CEO.

Permitting challenges included getting power through White Sands Missile Range and navigating state-level approvals. New Mexico rejected the initial transmission route in 2018. These delays led Senator Martin Heinrich of New Mexico to cite SunZia as a key reason for co-sponsoring Senate permitting reform that would coordinate federal approvals for interstate transmission lines.

Pattern Energy took over the transmission line project in 2022 and applied for a revised federal permit circumventing the missile range. Within less than two years, the company secured new approval. Then $11 billion in financing from global financial institutions, pension funds, and clean energy investors followed.

The project faced multiple lawsuits from tribal communities and environmental advocates, some remaining pending. The turbines immediately broke records for wind-generated power in California's energy supply when they came online.