Fred Beartrack of the Osage Nation's Department of Natural Resources recently excavated an orphaned oil well at Harvest Land Farms and discovered records were wrong. The well showed a cement plug on paper, but crews found no cement inside. Instead, the well remained open down to 2,400 feet.

"There was no cement, so the data was wrong," Beartrack said in a video posted to the Osage Nation's Facebook page. The crew had to clean the well to the bottom and properly fill it with cement, work that could take anywhere from two days to two months. Beartrack found only about a foot of cement at the top of the well, with nothing beneath it. Crews drilled past the freshwater zone and cemented the well from there up.

The Nation's Department of Natural Resources has plugged about 160 wells since the orphan well program began, with 70 to 80 plugged this year. Crews have inspected at least 2,500 to 2,700 wells across the Nation's reservation, which covers about 1,470,559 acres in northeastern Oklahoma. Beartrack said the department keeps finding new wells every quarter section it enters, many dating back decades to operators that disappeared or wells plugged to standards now considered inadequate.

The pace of well plugging accelerated after a change in federal oversight. On March 13, the Orphan Wells Plugging Office revised its tribal grant guidelines for Phase 1 and Phase 2 projects. Previously, the Bureau of Indian Affairs' Osage Agency approved every plugging permit the Nation filed.