Michigan Governor Gretchen Whitmer paused both pending and issued state permits for a plan to replace a segment of the Line 5 oil pipeline beneath the Straits of Mackinac on Tuesday. Whitmer directed regulators at the Michigan Department of Environment, Great Lakes and Energy to answer questions about the plan's threats to the environment. Those questions were raised by a Michigan Supreme Court ruling this summer that rejected a related Line 5 tunnel permit, saying environmental review was too narrow.
Line 5 has transported oil and natural gas liquids 645 miles between Ontario and Wisconsin since 1954. A four-mile segment passes through the Straits of Mackinac, which connects Lake Michigan to Lake Huron. Sensitive coastal and wetlands habitats are in the straits, and the area is sacred to Anishinaabe peoples, featuring in their creation story and serving as burial grounds for ancestors.
"I have always said my ultimate goal is to get Line 5 out of the water," Whitmer said. "Just one spill threatens irreparable damage to our water, our economy, and our way of life."
Pipeline owner Enbridge Energy proposed the tunnel replacement plan almost a decade ago. The company maintains the pipeline is safe. Enbridge spokesperson Ryan Duffy said regulators had already approved the pending permit, which renewed one from 2021. "Line 5 delivers the energy people depend on every day," Duffy said.
All 12 federally-recognized tribes in Michigan oppose the pipeline. Laura Berglan, senior attorney with Earthjustice representing three Michigan tribes, said protecting the Great Lakes and tribal resources requires transitioning away from Line 5.
The Line 5 tunnel project received federal approval, but the freeze on state permits leaves its future uncertain.