Cummins' Hydrogenics subsidiaries recommended in September that customers stop using HyLYZER electrolysers following a review of operating data. The company disclosed this in its November quarterly report without issuing a recall and said it was still assessing what modifications might be needed. Cummins had not established the cost of resolving the issue and warned the financial effect could be material.

Cummins' historical HyLYZER deployments represent roughly 145–213 MW, equivalent to 11–16% of the International Energy Agency's projected 1.3 GW global PEM electrolyser installed base at the end of 2026. The company did not publish how many HyLYZER plants the September recommendation covered.

Cummins announced in February that it intended to cease new commercial electrolyser activity while continuing existing customer commitments. Its 2025 Accelera restructuring and impairment charges reached $458 million across several actions, including the electrolyser retreat. The company is reducing specialist capacity at the same time installed equipment needs engineering attention.

Investigating field data, testing modifications, certifying repair procedures and maintaining proprietary controls requires specialist teams that must remain capable long after the sales pipeline has contracted. Estonia's Stargate Hydrogen took over Cummins' legacy HySTAT alkaline electrolyser platform and supplies replacement stacks and service for a fleet of more than 400 installations, showing how intellectual property and field-service expertise can survive an OEM exit.

For owners, the financial question depends on the purpose of the hydrogen. Air Liquide's 20 MW Bécancour installation and Linde's 35 MW Niagara Falls project serve companies with industrial hydrogen customers and alternative supply networks. Florida Power & Light's 25 MW Cavendish project converts electricity to hydrogen for blending into natural gas used in power generation. At an illustrative 55 kWh/kg of electrolyser electricity and 60% combined-cycle generation efficiency, about 36% of the original electricity returns after converting to hydrogen and burning it, before compression and storage.

Cummins made a separate exit from its low-pressure fuel-cell business in March 2026 with a $175 million net payment as part of a sale and claims settlement, producing a $199 million accounting charge. The PEM electrolyser repair costs remain unquantified.

The IEA's Global Hydrogen Review 2026 finds that global demand still sits overwhelmingly in traditional industry and refining. Only about one-fifth of newly signed low-emissions hydrogen offtake volumes in 2025 had firm contractual commitments.