Ontario Power Generation acknowledged that its first GE Vernova Hitachi BWRX-300 small modular reactor at Darlington will exceed its C$7.7 billion approved budget and miss its October 2030 commercial-operation target. OPG expects its engineering, cost and schedule review to be substantially complete by mid-2027, but has released no replacement cost or completion date.

OPG identified continuing first-of-a-kind reactor engineering as the reason, along with its effects on construction execution and supply-chain performance. The company started physical work while parts of the design governing that work were still evolving. The 2.1-million-pound reactor foundation is in place, turbine building work has progressed, and cooling-water tunnel equipment has been assembled, but these achievements have not resolved engineering dependencies, supplier requirements and delivery sequence.

The four-reactor program originally carried a C$20.9 billion budget, with C$6.1 billion budgeted for the first reactor, C$1.6 billion for common infrastructure and C$13.2 billion for Units 2 through 4. The financial model depends on later reactors becoming cheaper after the first teaches suppliers and builders how to execute the design.

OPG withdrew the Darlington SMR generation forecast from its 2027-2031 rate application filed with the Ontario Energy Board on November 10. Previously planned production of about 0.5 TWh in 2030 and 1.9 TWh in 2031 is no longer included in the filing.

The Independent Electricity System Operator's May 2026 LT2 energy procurement secured 1,115 MW of new wind and solar contracts with expected annual generation of about 2.37 TWh and a weighted average fixed price of C$88.84/MWh. Ontario also contracted 640 MW of battery capacity at C$563.48 per MW-business day.